The first 100 battery units have been installed at AGL’s 500-megawatt Tomago Battery in the Hunter, marking a major construction milestone for the $800 million project.
More than 400 battery units will make up the large-scale storage project. Concrete foundations have been laid, and work on the substation is well advanced, with the first of two main transformers arriving last week. Crews are also laying electrical cabling and installing inverters. More than 200 workers are currently involved in construction, which began in December 2025. AGL says the project remains on track for completion in late 2027.
Once operating, the battery will be able to run at full capacity for up to four hours, storing electricity when it is plentiful, including when wind and solar generation is strong, and releasing it into the grid later. In May 2026, the project was awarded underwriting support by the NSW Government through the Long-Term Energy Service Agreement scheme.

The milestone comes two months after AGL’s nearby 500-megawatt Liddell Battery, beside the former power station, reached practical completion. AGL says it is aiming to add a total of 12 gigawatts of renewable and firming capacity by the end of 2035.